Resolution 253/2025/QH15: Vietnam’s Energy Fast-Track Framework

Resolution 253/2025/QH15, in force since March 2026, fast-tracks energy projects: minister-approved plan updates, direct offshore-wind investors, wider DPPA.

Offshore wind turbines on the horizon and high-voltage transmission pylons on a Vietnamese coast at dawn.

Document facts

Issuing body: National Assembly of Vietnam (15th National Assembly, 10th session)

Document number: Resolution 253/2025/QH15 on mechanisms and policies for national energy development for the period from 2026 to 2030

Signed: December 11, 2025 (passed with 424 of 436 votes)

Effective: March 1, 2026

Status: In force; implemented through December 31, 2030

Unofficial English summary for reference only. Not a legal translation and not legal advice. The Vietnamese text linked at the end of this page is authoritative.

What the document does

Resolution 253/2025/QH15 is a 16-article framework turning Politburo Resolution 70-NQ/TW on national energy security into law. Its subject is procedure, not targets: it cuts the planning and approval steps that stalled energy projects, opens offshore wind to direct investor selection, widens direct power purchase agreements, and invites private capital, including small modular reactors, into generation.

Article 1 sets the scope: flexible updates to the national power plan and provincial network plans; power-project construction; offshore wind; direct power purchase; and oil, gas and coal projects, excluding those managed by the Steering Committee established under Prime Minister Decision 751/QD-TTg of April 11, 2025. Article 2 applies the Resolution to electricity-market actors, users and related parties, plus oil, gas and coal operators.

What changes in practice

A key mechanism is the plan-update procedure in Article 4. The Minister of Industry and Trade approves updates to the national power plan and reports to the Prime Minister, without the full Planning Law amendment procedure; provincial chairmen do the same for provincial network plans. Updates cover intergovernmental grid agreements, adding renewables and battery storage, or replacing slow projects. No strategic environmental assessment report is required. The limit is structural: an update may not change the plan’s major directions, or increase total installed capacity by power-source type.

Hands filing blank documents into a folder in a modern office with blank screens in the background.
Plan updates now move by ministerial decision under Article 4, without the full Planning Law amendment procedure. Photo illustration

Grid investment gets its own fast track. Under Article 5, grid projects in the power development plan or a provincial plan skip the investment-policy approval procedure entirely. Article 14 gives important and urgent national oil, gas and coal projects the same exemption.

The Prime Minister approves 2025 to 2030 offshore-wind projects and may simultaneously appoint the investor without a land-use auction or bidding, provided defense, security, sovereignty, marine-environment, maritime and oil-and-gas conditions are met and the project is in the power plan. A developer that already holds land-use rights may be directly appointed without bidding. For 2031 to 2035 offshore-wind projects, provincial chairmen take over, with written consensus from seven ministries including defense, public security and foreign affairs.

Article 8 makes the winning bid price the power purchase agreement price for most projects, with no forced renegotiation afterwards; the buyer must sign within 30 days. Thermal power, small modular reactors and offshore wind are excepted. Article 13 removes the private-wire ceiling tariff: contract prices are freely negotiated, and retailers in industrial parks, hi-tech parks, economic zones, urban areas and free-trade zones join as direct participants.

Article 16(5) is a supremacy clause: where the Resolution differs from other laws or National Assembly resolutions on the same matter, it prevails, unless a newer document offers better incentives, and the beneficiary may choose the most favorable treatment.

What changed from the previous rules

Before the Resolution, power-plan adjustments required the full Planning Law amendment procedure; most power projects needed investment-policy approval; offshore-wind investors were selected through normal land auctions and bidding; private-wire contracts were capped by ceiling tariffs; retailers participated only as authorized agents; and winning bid prices were renegotiated afterwards.

Since March 1, 2026, the MOIT Minister approves plan updates with a report to the Prime Minister; grid projects skip investment-policy approval; the Prime Minister directly appoints 2025 to 2030 offshore-wind investors; contract prices are freely negotiated with retailers joining directly; and the winning bid price stands as the contract price.

Defense, security and sovereignty conditions still apply to every offshore-wind project; projects must still be consistent with the approved power plan; plan updates still cannot raise total installed capacity by source type; and the Government still issues the detailed decrees.

Who is affected

The Resolution applies to everyone in the electricity value chain: generators, grid investors, power retailers, electricity users and their service providers, plus oil, gas and coal operators of important and urgent national projects. In practice, the primary parties affected are power developers, industrial buyers and retailers, bidding developers, and state-owned enterprises.

Notes for investors and operators

Power developers should check the Article 4 fast-track or the direct-appointment path: holding land-use rights may remove investor bidding entirely.

Industrial, hi-tech-park and free-trade-zone buyers can now contract directly as participants in their own right, with freely negotiated prices. The customer-eligibility list is determined by the Minister of Industry and Trade.

Bidders should price with discipline: the winning price becomes the contract price, signing closes within 30 days, and there is no post-win renegotiation. Project counsel should check this Resolution first whenever it conflicts with general investment or planning rules, under the Article 16(5) supremacy clause, while watching for newer documents with better incentives.

What businesses should do next

The framework is enacted law, but implementation is uneven. The MOIT fast-track machinery is visibly operational, from the 7,500 MW offshore-wind proposal debated on October 30 to this week’s Dong Hai 3 grid-connection adjustment. The promised Government decrees on offshore-wind financial-capacity criteria and small modular reactor procedures have not yet been issued. The National Assembly complaint on October 30 about renewable projects facing confusion across provinces concerned the related Resolution 254/2025/QH15, a separate instrument. Use the fast tracks open now; treat the unissued decrees as the remaining watch items.

Sources and the official text

Thu Vien Phap Luat, Resolution 253/2025/QH15 full text (Vietnamese, legal-database reproduction). https://thuvienphapluat.vn/van-ban/Tai-nguyen-Moi-truong/Nghi-quyet-253-2025-QH15-co-che-chinh-sach-phat-trien-nang-luong-quoc-gia-2026-2030-686772.aspx?tab=7

Quang Ninh Department of Industry and Trade portal, key content of Resolution 253/2025/QH15 (official provincial portal). https://www.quangninh.gov.vn/So/socongthuong/Trang/ChiTietTinTuc.aspx?nid=5000

Bao Tin Tuc (TTXVN), certifying and key provisions of Resolution 253/2025/QH15. https://baotintuc.vn/co-che-chinh-sach-phat-trien-nang-luong-quoc-gia-giai-doan-2026-2030-n20260101071918413.htm

vietnam.vn, breakthrough energy mechanisms (state external information portal). https://www.vietnam.vn/co-che-dot-pha-cho-phat-trien-nang-luong

Lexology, Vietnam’s Energy Policy: Key Updates and Strategic Directions (January 13, 2026). https://www.lexology.com/library/detail.aspx?g=164cf045-e1d0-4aab-ba4f-2c67db3a272f

Doanh nhan & Phap luat, offshore-wind investment authority under the energy framework (October 30, 2026). https://doanhnhan.baophapluat.vn/trao-tham-quyen-chap-thuan-chu-truong-dau-tu-mo-duong-cho-phat-trien-dien-gio-ngoai-khoi-89676.html

Vietnam News, National Assembly approves energy policy framework through 2030. https://vietnamnews.vn/Economy/1731727/national-assembly-approves-energy-policy-framework-through-2030.html

About this explainer: VoltViet prepared this summary in English from the official Vietnamese text so that investors and operators can follow what the document does. It is a reading aid, not a translation of record and not legal advice. Where any wording here differs from the Vietnamese text, the Vietnamese text governs. For decisions with legal or financial consequences, rely on the official text linked above and take advice from a qualified Vietnamese lawyer.